High caution - Lapsed - validity expired SIGNATURE GLOBAL PARK -II (Phase II) has 2 priority check(s), including Official status: lapsed, Registration expired. The captured RERA validity date was 29 Mar 2025, which is about 1 year and 3 months ago as of 08 Jul 2026.
Project check

SIGNATURE GLOBAL PARK -II (Phase II)

Sinatureglobal Homes Pvt Ltd

HR Regulating authority: GURUGRAM Project location: GURUGRAM
RERA IDRERA-GRG-859-2021
Statuslapsed
Valid until29 Mar 2025
Documents found34
What we know Lapsed - validity expired

SIGNATURE GLOBAL PARK -II (Phase II) has 2 priority check(s), including Official status: lapsed, Registration expired. The captured RERA validity date was 29 Mar 2025, which is about 1 year and 3 months ago as of 08 Jul 2026. These are public-record observations, not a final safety rating.

What we don't know yet 34 need manual reading

34 documents captured; 34 need manual reading or text extraction before relying on document contents.

Questions to put to Sinatureglobal Homes Pvt Ltd

These are written for this project. Take them to the builder, broker, lender, or lawyer.

Regulating authorityGURUGRAM
Project districtGURUGRAM
Project locationVillage Dhunela, Sector-36
Completion-

Why we say this

ImportanceConfidenceIssue / FindingWhat We FoundSource
Important High Official status: lapsed Official Haryana RERA list labels this project as lapsed. -
Important High Registration expired Registration valid-up-to date is before the latest check date. -
Note Medium Occupation/completion certificate found A linked project document appears to refer to an occupation or completion certificate. -

Documents on file

34 documents captured; 34 need manual reading or text extraction before relying on document contents. The categories below show what to ask for before booking, lending, or signing.

RERA registration certificate / status 0 documents

Confirms the project registration, validity, promoter, phase, and official status.

Addendum, corrigendum, amendments 1 document

Shows whether registration details, timelines, layout, or disclosures changed after registration.

Licence, approvals, sanctioned layout / building plan 21 documents

Helps verify that the project has official permissions for the disclosed plan and construction.

Completion / occupation / handover documents 12 documents

Important for possession, utilities, handover, and whether the project is legally ready to occupy.

Financial and default declarations 0 documents

Can reveal cash-flow, non-default, encumbrance, or declaration material relevant to buyer risk.

Agreement, allotment, payment and buyer terms 0 documents

The buyer's contract should match RERA disclosures on area, possession, payment, refund, and penalties.

Show captured document checklist

RERA registration certificate / status

Confirms the project registration, validity, promoter, phase, and official status.

Ask:

Ask for the latest certificate or portal printout showing current validity.

  • No matching captured document found yet. Ask the builder or advisor for this.

Addendum, corrigendum, amendments

Shows whether registration details, timelines, layout, or disclosures changed after registration.

Ask:

Ask what changed and whether it affects your tower, unit, possession, or amenities.

  • Extension No. 16 of 2023 dated 19.06.2023 not text-read yet

Licence, approvals, sanctioned layout / building plan

Helps verify that the project has official permissions for the disclosed plan and construction.

Ask:

Ask for sanctioned plans, licence approvals, and any renewal or revision documents.

  • BUILDING PLAN not text-read yet
  • BUILDING PLAN not text-read yet
  • BUILDING PLAN not text-read yet
  • BUILDING PLAN not text-read yet
  • + 17 more document(s) in this category

Completion / occupation / handover documents

Important for possession, utilities, handover, and whether the project is legally ready to occupy.

Ask:

Ask for completion certificate, occupation certificate, or authority handover proof where applicable.

  • PROJECT CONTINUATION- RC/REP/HARERA/GGM/42 of 2021/7(3)/82/2025/24 DATED 22.08.2025 not text-read yet
  • SERVICE ESTIMATES not text-read yet
  • DETAILED PROJECT INFORMATION FOR REGISTRATION OF PROJECT not text-read yet
  • COMPLETION CERTIFICATE not text-read yet
  • + 8 more document(s) in this category

Financial and default declarations

Can reveal cash-flow, non-default, encumbrance, or declaration material relevant to buyer risk.

Ask:

Ask whether there are dues, loans, mortgages, defaults, or encumbrances affecting the project.

  • No matching captured document found yet. Ask the builder or advisor for this.

Agreement, allotment, payment and buyer terms

The buyer's contract should match RERA disclosures on area, possession, payment, refund, and penalties.

Ask:

Ask your lawyer to compare the sale agreement with the latest RERA disclosures before signing.

  • No matching captured document found yet. Ask the builder or advisor for this.
How we built this page. Findings come from captured public RERA portal metadata, official status/date fields, document records, and source links. A paid report adds manual review and a shareable buyer memo.