High caution - Lapsed - validity expired Signature Global Park III-(Phase-2) has 2 priority check(s), including Official status: lapsed, Registration expired. The captured RERA validity date was 30 Aug 2025, which is about 10 months ago as of 09 Jul 2026.
Project check

Signature Global Park III-(Phase-2)

SIGNATUREGLOBAL HOMES PVT LTD

HR Regulating authority: GURUGRAM Project location: GURUGRAM
RERA IDRERA-GRG-862-2021
Statuslapsed
Valid until30 Aug 2025
Documents found28
What we know Lapsed - validity expired

Signature Global Park III-(Phase-2) has 2 priority check(s), including Official status: lapsed, Registration expired. The captured RERA validity date was 30 Aug 2025, which is about 10 months ago as of 09 Jul 2026. These are public-record observations, not a final safety rating.

What we don't know yet 28 need manual reading

28 documents captured; 28 need manual reading or text extraction before relying on document contents.

Questions to put to SIGNATUREGLOBAL HOMES PVT LTD

These are written for this project. Take them to the builder, broker, lender, or lawyer.

Regulating authorityGURUGRAM
Project districtGURUGRAM
Project locationVillage Dhunela, Sector 36, Sohna, Distt. Gurugram
Completion-

Why we say this

ImportanceConfidenceIssue / FindingWhat We FoundSource
Important High Official status: lapsed Official Haryana RERA list labels this project as lapsed. -
Important High Registration expired Registration valid-up-to date is before the latest check date. -

Documents on file

28 documents captured; 28 need manual reading or text extraction before relying on document contents. The categories below show what to ask for before booking, lending, or signing.

RERA registration certificate / status 0 documents

Confirms the project registration, validity, promoter, phase, and official status.

Addendum, corrigendum, amendments 1 document

Shows whether registration details, timelines, layout, or disclosures changed after registration.

Licence, approvals, sanctioned layout / building plan 21 documents

Helps verify that the project has official permissions for the disclosed plan and construction.

Completion / occupation / handover documents 6 documents

Important for possession, utilities, handover, and whether the project is legally ready to occupy.

Financial and default declarations 0 documents

Can reveal cash-flow, non-default, encumbrance, or declaration material relevant to buyer risk.

Agreement, allotment, payment and buyer terms 0 documents

The buyer's contract should match RERA disclosures on area, possession, payment, refund, and penalties.

Show captured document checklist

RERA registration certificate / status

Confirms the project registration, validity, promoter, phase, and official status.

Ask:

Ask for the latest certificate or portal printout showing current validity.

  • No matching captured document found yet. Ask the builder or advisor for this.

Addendum, corrigendum, amendments

Shows whether registration details, timelines, layout, or disclosures changed after registration.

Ask:

Ask what changed and whether it affects your tower, unit, possession, or amenities.

  • Extension No. 27 of 2024 dated 11.12.2024 not text-read yet

Licence, approvals, sanctioned layout / building plan

Helps verify that the project has official permissions for the disclosed plan and construction.

Ask:

Ask for sanctioned plans, licence approvals, and any renewal or revision documents.

  • BUILDING PLAN- TYPE D- PLOT-1,3,5,7,9,11,13 not text-read yet
  • SUPERIMPOSED LAYOUT PLAN not text-read yet
  • BUILDING PLAN- TYPE A -PLOT-1,3,5,7 not text-read yet
  • BUILDING PLAN- TYPE A-PLOT-2,4,6 not text-read yet
  • + 17 more document(s) in this category

Completion / occupation / handover documents

Important for possession, utilities, handover, and whether the project is legally ready to occupy.

Ask:

Ask for completion certificate, occupation certificate, or authority handover proof where applicable.

  • CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT not text-read yet
  • CASH FLOW STATEMENT OF THE PROPOSED PROJECT not text-read yet
  • DEMARCATION PLAN not text-read yet
  • ZONING PLAN not text-read yet
  • + 2 more document(s) in this category

Financial and default declarations

Can reveal cash-flow, non-default, encumbrance, or declaration material relevant to buyer risk.

Ask:

Ask whether there are dues, loans, mortgages, defaults, or encumbrances affecting the project.

  • No matching captured document found yet. Ask the builder or advisor for this.

Agreement, allotment, payment and buyer terms

The buyer's contract should match RERA disclosures on area, possession, payment, refund, and penalties.

Ask:

Ask your lawyer to compare the sale agreement with the latest RERA disclosures before signing.

  • No matching captured document found yet. Ask the builder or advisor for this.
How we built this page. Findings come from captured public RERA portal metadata, official status/date fields, document records, and source links. A paid report adds manual review and a shareable buyer memo.
Need a deeper read?

Order a buyer report for Signature Global Park III-(Phase-2).

Soft launch offer: one free report per email where useful public data exists. We hand-review the captured record and prepare practical questions for the transaction.